What is a Factory Acceptance Test Checklist?

A factory acceptance test checklist is a comprehensive document that outlines the criteria, procedures, and requirements to assess and verify equipment and system quality, functionality, and conformity. Quality managers, design engineers, operators, and maintenance personnel use this as a tool to test and ensure that newly produced equipment works according to design specifications before installation and operation.

Why Use a Factory Acceptance Test Checklist?

Overlooked equipment discrepancies can lead to installation problems on site, which can wreak havoc on a project schedule. Prior to shipment, quality managers should resolve nonconformity at the factory so that the clients’ new processing lines are up and ready to go on time.

When FATs are conducted with the help of checklists, the following issues can be proactively identified and avoided:

  • Poor Machine Quality or Craftsmanship

  • Nonconformity to Regulatory or Sanitary Specifications, especially for pharmaceutical or nutraceutical manufacturing (e.g., American Society of Mechanical Engineers (ASME), International Electrotechnical Commission (IEC))

  • Lack of Appropriate Machine Guarding and Labels (e.g., Lock Out Tag Out (LOTO) labels and procedures, compliance with Occupational Health & Safety Administration (OSHA) standards)

  • Lower than Expected Throughput

Hence, using a factory acceptance test checklist template can reduce costly project delays by ensuring the completion of factory acceptance test and its protocols—such as standard work procedures, certificates of compliance, and welding process qualifications, and implementing the proper factory acceptance test procedure.

What to Include in a Factory Acceptance Test Template?

A good factory acceptance test checklist should enable quality managers to verify the following and more:

  • Conformance to specifications

  • Certificates of compliance

  • Welding processes qualifications

  • As-built technical drawings

  • Instruments calibration certificates

  • Standard work procedures

  • Equipment data sheets

  • Materials data sheets

  • Control system

  • Standard maintenance procedures

  • Training materials

  • Ergonomic assessment

Some other elements you must consider including in the checklist are personnel checks, post-FAT template, completion page, and sign-off.

Perform Factory Acceptance Test Using a Checklist

Conducting a factory acceptance test using a checklist is a critical step to ensure that equipment or systems meet specified requirements and quality standards before they are delivered to the customer. Hence, properly following a structured process is essential to achieving the desired outcomes and avoiding potential issues.

Follow these steps to effectively carry out a FAT with the help of a checklist:

1. Prepare for the FAT testing

Ensure that all parties involved, including the customer and the manufacturer, have reviewed and agreed upon the FAT checklist. Also, verify that the testing environment is set up and that all necessary documentation, tools, and personnel are in place.

2. Perform the tests

Test the equipment or system’s various functions, performance parameters, and safety measures. Make sure to document the results of each test, including any deviations or discrepancies from the checklist.

3. Document real-time observation

Designated individuals, including customers and third-party inspectors, must observe and document their real-time observations during the tests using the checklist. They can verify that these are conducted impartially and that the equipment meets the acceptance criteria.

4. Address deviations and issues

If the equipment fails to meet any of the acceptance criteria or if discrepancies are found during testing, develop a plan to address them. The manufacturer is responsible for rectifying the problems and retesting the equipment until it complies with the requirements specified in the checklist.

5. Finalize documentation and obtain approval

Once all tests have been successfully completed, and any issues resolved, finalize the documentation of the FAT results. This should include a summary of the tests, deviations, resolutions, and any relevant observations. Make sure to obtain approval from all parties involved before proceeding with the shipment of the equipment or system.

FAT Report Example

A factory acceptance test report serves as a crucial documentation tool, summarizing the results and findings of the FAT and helping you understand how it supports the assurance of a successful project outcome.

Here’s a factory acceptance test example when exported as a PDF report:

Factory Acceptance Test Checklist Sample Report

Factory Acceptance Test PDF Report | SafetyCulture

This is a CTA image

Still looking for a checklist?

Create a custom checklist template instantly with AI

FAQs About Factory Acceptance Test Checklists

JT

Article by

Jona Tarlengco

SafetyCulture Content Specialist

View author profile

Related resources you might like

Powered by

Factory Acceptance Test Template

This factory acceptance test report template is a comprehensive validation test for outboard equipment (external effects unit), including AC Power Test, Audio Test, Video Test, Control and Performance Test, and Network Test. Quality managers in the manufacturing facility can customize this template based on the specifications of the equipment to undergo a factory acceptance test.

Powered by

Equipment FAT Checklist

This equipment FAT checklist can be used for the commissioning of burners/boilers in an industrial or commercial power plant. Easily customize or build your own checklist using SafetyCulture’s template editor to meet specific equipment design requirements and fulfill company needs.

Powered by

Site Acceptance Test Checklist

After the factory acceptance test, equipment delivery, and site installation, the client conducts a site acceptance test, ideally with the quality manager from the manufacturing facility. Use this checklist as a guideline in conducting site acceptance tests and automatically generate a shareable report the moment you finish the SAT.

Articles

Water Quality Software

Discover the most outstanding water quality software and deliver clean and potable water to the community you serve with your top pick.

A Guide to Zero Defects

Learn about the zero defects philosophy, what it means, and how to achieve zero defects in quality management.

Construction Quality Control Checklist

Ensure compliance with regulatory standards and specifications by using construction quality control checklists.